Permit to work
A formal, time-limited authorisation for high-risk work, confirming that named precautions are in place before it starts and closed out when it ends.
A permit to work is a control for work whose risk depends on specific precautions being in place for a defined period: hot works, confined space entry, excavation near services, electrical isolation, work at height in certain circumstances, lifting operations, demolition, breaking ground, night works, asbestos, temporary works, live services. An authorised person who is not doing the work walks the job, confirms each precaution against a checklist, sets the start and expiry times, and signs. The person in charge of the work accepts by signature. When the work ends, both sign the close-out, having checked the area is safe.
The permit does not replace the RAMS; it sits on top of it for that shift. Its value is that it forces a second person to confirm the precautions at the moment they matter, and that it is time-limited: a new day is a new permit. The commonest failures are permits issued from the office without a walk round, permits that run for a week, and permits closed out without anyone checking the fire watch was done.
Where it comes from
- Health and Safety at Work etc. Act 1974 s.2: safe systems of work.
- Confined Spaces Regulations 1997 reg.4: safe system of work, for which a permit is the recognised means.
- Electricity at Work Regulations 1989 reg.13 and reg.14: isolation and work on live conductors.
- HSE guidance HSG250 (Guidance on permit-to-work systems).
Questions people ask
Who can issue a permit to work?
An authorised person appointed by the contractor, competent for that type of work, and not the person doing it. On a small site that is usually the site manager or supervisor. The issuer walks the job; a permit signed at a desk is a form, not a control.
How long can a permit last?
One shift, or a shorter stated period. If conditions change, it is suspended. A permit is re-issued, not extended.